Construction work on Luitpoldstrasse

Dear guests,

our Luitpoldstraße is finally being completely renovated and redesigned.


Unfortunately, this is associated with certain restrictions (possible construction noise during the day, etc.).


As a fair host, we already tell you at this point
the key data of the project of the city of Nuremberg with:


  • Type of construction project: complete renewal of the road surface, new trees and beds, racks for bicycles and benches
  • general start of construction: April 2022 (postponed to mid-June 2022)
  • Planned end of construction: April 2023 (postponed to summer 2023) (postponed again to November 2023)
  • Regular operation: 7:00 a.m. - 5:00 p.m. (sometimes until 6:00 p.m.) Monday to Friday (in exceptional cases also on Saturdays)
  • direct access (loading and unloading, max. 3 minutes) is still (theoretically) possible (during the daytime construction work, access will only be granted in justified cases) - we expressly recommend that those arriving by car first park in the parking garage at Sterntor (only a few hundred meters away).


Progress in detail can be found in this link of the SÖR (service company public space Nuremberg).

We wish you a pleasant stay in our house
and are available to answer any questions you may have about the makeovers via the
sicherheit@probst.bayern gladly available.